QUALITY IS JOB ONE
WE ARE ISO9002 CERTIFICATDE COMPANY
|
INSTALLATION
GIDE |
In the installation
of an access floor, there are certain criteria that should be followed.
Any fault in installation may cause problem. Generally, an installation
should follow the following steps.
|
Step
1.Measure the room and draw grids.
Check the room and get accurate sizes of the room.Figure out how
many rows will be best.Decide which is the start point. Then draw
lines with chalk on the base ground to form drawn grids.Sympolize
where the perforated panels and outlet box should be install. Check
If this installation plan is the best. Try to improve it if possible.
Step 2. Glue Pedestals and Bolt stringers
Glue pedestals according the drawn grids on the sub-ground.If stringer
are applied, bolt stringers to the pedestals to form taised grids.
Step 3. Install panels
Lay panels from the start point one row after another.Pay special
attention to perforated panels , outlet boxes.Corners and boundary
need also special sized or trimmed panels.
Step 4. Floor Covering Arrangement
Clean panel surfaces.Sometimes was are needed to apply the coverings.Some
users select anti-static carpets.
|
click for picturesSPECIALIZED STEEL ACCESS
HOUR MANUFACTURER |